Whitelock Parkway - Highway 99 Interchange Summary
The Road Ahead
An In-Depth Look at the Whitelock Parkway & SR-99 Interchange Project
2028
Anticipated Construction Start
2026
Environmental Review Completion
38.7%
Unsecured CIP Funding
2030s
Projected Opening for Motorists
A Decade in the Making: Project Timeline
Large infrastructure projects are a marathon, not a sprint. The journey from initial concept to an operational interchange spans many years of planning, review, and construction.
Project Initiation (2020)
The Project Study Report was approved, officially kicking off the development process by defining the project's initial scope and needs.
Environmental & Design Phase (2021-2027)
The current, multi-year phase focuses on rigorous environmental studies (CEQA/NEPA), refining design alternatives, and beginning Right-of-Way acquisition.
Anticipated Construction (2028)
Contingent on securing funding and completing all prior phases, physical construction is expected to begin.
Projected Opening (Early to Mid-2030s)
Given the scale of construction, the interchange is projected to open for public use several years after construction begins.
The Path to Construction
Building an interchange is a sequential process with critical dependencies. The project is currently navigating the complex Environmental & Design phase, a crucial step before major construction funding can be secured and work can begin.
1. Environmental & Design
IN PROGRESS
2. Funding Secured
PENDING
3. Construction
FUTURE
Funding the Future
The interchange is part of the city's 5-Year Capital Improvement Program. While over 60% of the program is funded, a significant portion for projects like this relies on securing future grants.
Project Scope & Community Benefits
What's Being Built?
- 🛣️A new interchange connecting Whitelock Pkwy and SR-99.
- 🚗High Occupancy Vehicle (HOV) lane integration on SR-99.
- 🚶♀️A dedicated pedestrian and bicycle overcrossing for safe, non-motorized travel.
- 🔄Improvements and modifications to local roads like Lotz Pkwy and E/W Stockton Blvd.
Anticipated Benefits
- 📉Alleviate traffic congestion driven by current and future growth.
- 🌍Support long-term, sustainable urban development in Elk Grove.
- ↔️Improve mobility, connectivity, and safety for all modes of travel.
- 🌳Enhance quality of life by connecting communities to recreational areas.
#8647 #NoKings #ProDemocracy
Status Report: Whitelock Parkway and SR-99 Interchange Project, Elk Grove, California
Executive Summary
The proposed Whitelock Parkway and State Route 99 (SR-99) Interchange project in Elk Grove is a critical infrastructure initiative designed to address growing traffic demands. The project is currently in the Project Approval and Environmental Document (PA&ED) Phase, a pivotal stage for defining project alternatives and completing necessary environmental studies.
June 19, 2026, a timeline that has experienced an extension, reflecting the inherent complexities of regulatory compliance.
Concurrently, final design and Right-of-Way (ROW) acquisition efforts commenced in January 2024 and are actively progressing alongside the environmental phase.
anticipated to begin in 2028.
Given the anticipated construction start in 2028 and the multi-year build period typical for infrastructure projects of this magnitude, the Whitelock Parkway and SR-99 Interchange is not expected to be open for motorist use until well after 2028, likely extending into the early to mid-2030s.
1. Project Overview and Strategic Importance
Project Description
The State Route 99 (SR-99) and Whitelock Parkway Interchange Improvements Project represents a substantial undertaking aimed at enhancing regional transportation infrastructure within the City of Elk Grove, California. The project’s core involves the construction of a new interchange at the intersection of Whitelock Parkway and SR-99.
The comprehensive scope of this project extends beyond merely facilitating vehicular traffic. Key components include the integration of High Occupancy Vehicle (HOV) carpool lanes on SR-99 within the project limits, designed to promote more efficient use of the highway.
Strategic Purpose
The primary impetus behind the proposed interchange is to alleviate the expected increase in traffic demand. This demand is a direct consequence of ongoing residential growth and planned future developments in the vicinity of Whitelock Parkway.
The context for this need is rooted in existing and projected congestion along the SR-99 corridor. Certain segments, notably Elk Grove Boulevard between SR-99 and Elk Grove-Florin Road, already operate at a "Level of Service F" (LOS F), which signifies severe traffic delays and highly congested conditions.
Key Agencies Involved
This major public infrastructure project is a collaborative effort between two principal entities: the California Department of Transportation (Caltrans) and the City of Elk Grove.
Holistic Transportation Planning
The detailed descriptions of the Whitelock Parkway and SR-99 Interchange project consistently highlight components that extend beyond merely increasing vehicle capacity. The inclusion of High Occupancy Vehicle (HOV) lanes, a dedicated pedestrian overcrossing, and improvements to local roads
This comprehensive design suggests a strategic evolution in urban development. It moves towards more sustainable and multi-modal transportation solutions. The integration of pedestrian and bicycle infrastructure is not merely an auxiliary feature but a fundamental aspect of the project's design. This reflects a recognition that long-term urban vitality and an improved quality of life necessitate diverse mobility options, extending beyond reliance on individual automobiles. This progressive approach is consistent with the City of Elk Grove’s stated commitment to fostering a "greener Elk Grove".
2. Project Development Lifecycle and Current Status
Project Initiation Phase
The foundational phase of the Whitelock Parkway and SR-99 Interchange project, known as Project Initiation, reached its conclusion with the approval of a Project Study Report - Project Development Support (PSR-PDS) document. This critical document, which serves to identify and estimate the project's initial scope, schedule, and support costs necessary for future studies, received approval on August 9, 2020.
Current Phase: Project Approval and Environmental Document (PA&ED)
Following the completion of the PSR-PDS, the project officially advanced into its current and highly analytical phase: the Project Approval and Environmental Document (PA&ED) phase.
The central purpose of the PA&ED phase is to conduct a thorough examination and refinement of various project alternatives. This involves carrying out all necessary environmental studies, with the ultimate goal of producing an approved Project Report, a California Environmental Quality Act (CEQA) environmental document, and a National Environmental Policy Act (NEPA) environmental document.
The environmental review and permitting processes are currently "IN PROGRESS".
June 19, 2026.
The PSR-PDS identified six distinct build alternatives for the interchange, including variations of Tight Diamond and Diverging Diamond configurations, with options for realigning SR-99. The selection of the final design is constrained by the proximity of sensitive adjacent areas, specifically the Elk Grove Regional Park and the Elk Grove Historical Society Museum.
Final Design and Right-of-Way (ROW) Acquisition
These essential pre-construction activities, which encompass detailed engineering and the process of securing necessary land for the project, began in January 2024 and are actively underway.
Complexity and Regulatory Hurdles as Timeline Drivers
The project's progression through the environmental review and permitting phase, which has been underway since April 2021 with an estimated completion date of June 2026
3. Funding Landscape and Financial Outlook
Overall Capital Improvement Program (CIP) Context
The Whitelock Parkway/State Route 99 Interchange Project is a significant and integral component of the City of Elk Grove's broader 2025-2030 Capital Improvement Program (CIP). This comprehensive program outlines approximately $293.28 million in proposed capital projects scheduled over the next five fiscal years.
As detailed in the May 2025 City Council Staff Report, the funding status within the CIP indicates that 61.35% ($179.94 million) of all projects are currently funded. However, a substantial portion, 38.65% ($113.34 million), currently has unsecured funding.
Funding for Whitelock Interchange
While specific, fully secured funding for the entire construction of the Whitelock Parkway/State Route 99 Interchange Project is not yet detailed, the City of Elk Grove has explicitly stated its strategy to "continue to pursue grants to fund construction".
Notably, the Request for Proposals (RFP) for preliminary engineering services for the project, issued in June 2025, specifies that "This Project will use Federal grant funds" for these initial engineering and environmental documentation services.
State-Level Funding Context
California, under Governor Newsom's administration, has demonstrated a strong commitment to infrastructure investment. Recent announcements include nearly $5 billion in funding for various projects, including state highways, primarily sourced from Senate Bill (SB) 1 (the Road Repair and Accountability Act of 2017), which utilizes gas tax revenues.
City's Fiscal Health
The City of Elk Grove's overall financial stability provides a positive backdrop for the project. The City Council adopted a balanced $411 million budget for the 2025-26 fiscal year. This budget includes maintaining a robust 25% reserve and fully funding an Opportunity Reserve, which adds flexible funding for unforeseen events or community needs.
Project Funding Status Overview
The table below provides a structured overview of the funding status across different phases of the Whitelock Parkway and SR-99 Interchange Project.
Project Phase | Current Funding Status | Primary Funding Sources | Notes/Details |
Project Initiation | Secured | City Funds, State Funds | PSR-PDS approved August 9, 2020. |
Environmental Review & Permitting | Secured (for preliminary engineering) | Federal Grants | Preliminary engineering services funded by Federal grants. |
Final Design & Right-of-Way Acquisition | Partially Secured / Actively Pursuing | City Funds, Anticipated Grants | Began January 2024, ongoing. |
Construction | Unsecured / Actively Pursuing | Future Grants (Federal, State) | City will continue to pursue grants. |
Funding as a Critical Path Element and Source of Uncertainty
The City's 2025-2030 Capital Improvement Program report explicitly states that a significant portion of its projects, including the Whitelock Interchange, rely on "unsecured funding" from future grants, and critically, that the "delivery timing is also uncertain" for these projects.
While the environmental and design phases are progressing with some secured funding, the major construction phase, anticipated for 2028, is highly contingent on the successful and timely securing of these large grants. This dependence on external funding sources introduces a significant variable that is not entirely within the City's direct control. Therefore, the 2028 construction start date should be viewed as an anticipation or target, rather than a firm commitment, as delays in grant acquisition could inevitably push back the construction timeline. This makes funding acquisition the next major critical path item after environmental clearance.
4. Construction and Operational Timelines
Environmental Review and Permitting Completion
The completion of the environmental review and permitting phase is a foundational prerequisite for the commencement of physical construction. This critical phase is estimated to be completed by June 19, 2026.
Final Design and Right-of-Way Acquisition
These critical pre-construction activities, which include detailed engineering and the process of securing necessary land parcels for the project, commenced in January 2024 and are actively underway.
Anticipated Construction Start
Based on the most recent official City of Elk Grove documents, construction for the Whitelock Parkway/State Route 99 Interchange Project is anticipated to begin in 2028.
Projected Completion and Opening for Motorist Use
No specific completion date for the entire interchange project or an exact opening date for motorist use is provided in the most recent official documents. However, considering the anticipated construction start in 2028 and the inherent scale and complexity of a new highway interchange, construction would typically span several years. For context, another major SR-99 connector project in a different region has a projected completion for its entire scope by 2042
well after 2028, likely in the early to mid-2030s.
Discrepancy Analysis
An older news report from August 2024
outdated and directly contradicted by more recent and authoritative official government sources.
Key Project Milestones and Anticipated Dates
The table below summarizes the key milestones and their anticipated timelines for the Whitelock Parkway and SR-99 Interchange Project.
Milestone/Phase | Start Date (Actual) | Estimated Completion/Anticipated Date | Key Sources | Notes |
Project Study Report (PSR-PDS) Approval | August 9, 2020 | Completed | Foundation for subsequent studies. | |
Project Approval & Environmental Document (PA&ED) Phase Start | August 2020 (following PSR-PDS) | Ongoing | Lead Agency: Caltrans. | |
Environmental Review & Permitting Completion | April 21, 2021 | June 19, 2026 | Process experienced an extension. | |
Draft EIR & Project Design Completion | Late 2022 | FY27 (June 30, 2027) | Aligns with environmental review. | |
Final Design & Right-of-Way Acquisition Start | January 2024 | Ongoing | Concurrent with environmental phase. | |
Anticipated Construction Start | N/A | 2028 | Contingent on funding and prior phase completion. | |
Estimated Opening for Motorist Use | N/A | Post-2028 (Early to Mid-2030s) | Estimate based on project scale and typical construction duration. |
The Long Game of Infrastructure Development and Public Patience
The project's timeline, from the PSR-PDS approval in 2020
This extended timeline underscores the immense scale, inherent complexity, and extensive bureaucratic processes involved in modern highway infrastructure development in California. It signifies that such projects are not quick solutions but rather long-term strategic investments that require sustained political will, consistent funding, and continuous collaboration among multiple agencies. The significant gap between public anticipation for "traffic relief"
5. Community Engagement and Anticipated Benefits
Community Feedback and Concerns
Public input has been an integral component of the project's development. Public feedback was actively sought for the proposed interchange.
The project's current description explicitly includes a bike and pedestrian overcrossing of SR-99.
Anticipated Benefits
The Whitelock Parkway and SR-99 Interchange project is poised to deliver several significant benefits to Elk Grove residents and commuters:
Traffic Relief: A primary objective is to alleviate the expected increase in traffic demand driven by ongoing residential growth and planned future developments in the area.
1 The interchange is anticipated to provide much-needed relief for motorists navigating the currently congested SR-99 corridor15 , particularly given that some segments already operate at unacceptable levels of service.7 Improved Mobility and Connectivity: By constructing a new interchange, along with auxiliary lanes and modifications to local roads, the project aims to significantly improve overall highway operation and mobility within the project limits.
1 This will enhance the efficiency of regional travel and local circulation.Enhanced Multi-Modal Options: The deliberate inclusion of a bike and pedestrian overcrossing
1 will provide safer and more convenient non-motorized transportation options. This feature is crucial for connecting communities and recreational areas, such as Elk Grove Park, and aligns with the City's broader sustainability initiatives and commitment to "gaining a greener Elk Grove".5 Support for Urban Growth: As a key component of the City's General Plan, the project is fundamental to supporting and accommodating ongoing urban development and future growth in Elk Grove.
1 It provides the necessary infrastructure to facilitate planned expansion.
Balancing Growth and Livability through Integrated Design
The project is fundamentally driven by the need to accommodate "expected increased traffic demand due to existing residential growth and planned future developments"
This dynamic suggests a conscious effort to balance the demands of economic and population growth with the imperative of preserving and enhancing community livability. The design choices indicate a more nuanced and integrated approach to infrastructure development, where the project serves not only as a traffic solution but also as a catalyst for improved quality of life and sustainable transportation options. This reflects a progressive urban planning philosophy that seeks to build a city that meets both current and future needs in a holistic manner.
6. Challenges and Future Considerations
Funding Acquisition
The most substantial challenge for the Whitelock Parkway Interchange project lies in securing the significant funding required for its construction phase. A considerable portion (38.65%, or $113.34 million) of the City's overall Capital Improvement Program projects, which includes the Whitelock Interchange, currently relies on "unsecured funding" from future grants.
Regulatory Complexity and Environmental Clearance
The lengthy and extended environmental review and permitting process, with an estimated completion date of June 2026
Inter-Agency Coordination
As the project directly interfaces with a Caltrans-managed facility (SR-99), continuous and close "collaboration and approval by Caltrans will be required throughout all phases of the project".
Public Expectation Management
While the interchange is a critical long-term solution for traffic relief in Elk Grove
Long-Term Vision vs. Immediate Needs
The project is an integral part of Elk Grove's long-term vision for sustainable growth and improved infrastructure.
Interdependencies and Risk Factors Driving Project Pace
The project's progression is characterized by a sequential and interdependent chain of phases. Environmental clearance must largely precede final design and right-of-way acquisition, which in turn must largely be complete before substantial construction funding can be secured. Only after these prerequisites are met can physical construction commence. The available information explicitly highlights that the environmental review has already been extended
Conclusion
The proposed Whitelock Parkway and SR-99 Interchange project represents a vital, long-term infrastructure initiative for the City of Elk Grove. It is strategically designed to alleviate future traffic congestion resulting from continued urban growth and to significantly enhance multi-modal connectivity within the community.
The project is steadily advancing through its complex development lifecycle. It is currently in the crucial Project Approval and Environmental Document (PA&ED) phase, with environmental clearance anticipated by June 2026.
While the preliminary planning and design phases have secured some funding, the substantial construction phase, which is anticipated to commence in 2028, remains largely dependent on the successful acquisition of future grants.
Given the anticipated 2028 construction start and the multi-year construction period typical for infrastructure projects of this scale, the Whitelock Parkway and SR-99 Interchange is not expected to be open for motorist use until well after 2028, likely in the early to mid-2030s.
This project exemplifies the intricate balance required in modern urban development: addressing the demands of growth, navigating rigorous environmental regulations, and securing substantial financial investment. Continued monitoring of funding announcements and environmental approvals will be key to accurately tracking the project's progress and providing updated timelines to the community.