55-hour partial shutdown this coming weekend on I-5; Elk Grove to be affected
https://www.elkgrovenews.net/2020/05/55-hour-partial-shutdown-this-coming.html
Starting 8 p.m. on Friday, May 15, and continuing until 5 a.m. on Monday, May 18, Caltrans is planning a 55-hour partial highway closures on Interstate 5 for the SAC 5 Corridor Enhancement Project.
This 55-hour lane closure will involve four locations, causing delays for both southbound and northbound directions and close on and off-ramps.
SCHEDULE:
• From 8 p.m. Friday, May 15 through 5 a.m. Monday, May 18.
LOCATIONS:
• NB I-5 will be limited to one lane from Laguna Blvd. to Pocket Rd. (3.5 miles)
• SB I-5 will be limited to one lane from Pocket Road to Laguna Blvd.
• NB I-5 will be limited to two lanes from J Street to Richards Blvd. (1.5 miles)
• SB I-5 will be limited to two lanes from Richards Blvd to J Street
RAMP CLOSURES:
• WB Laguna Blvd On-Ramp to NB I-5
• NB I-5 Off-Ramp to Cosumnes Blvd
• EB Cosumnes Blvd On-Ramp to NB I-5
• WB Cosumnes Blvd On-Ramp to NB I-5
• L Street On-Ramp to NB I-5
• I Street On-Ramp to NB I-5
• Richards Blvd On Ramp to SB I-5
We are expecting heavy traffic at these locations during the day. Please consider alternate routes, such as State Route 99 to avoid being stuck in heavy traffic.
A 55 mph speed limit through the construction zone will be strictly enforced. Any motorists caught speeding will be cited so please slow for the cone zone.
For more information on this project text ‘FixSac5’ to 58632 or visit www.FixSac5.com
For real-time traffic, click on Caltrans QuickMap quickmap.dot.ca.gov/ or download the QuickMap app from the App Store or Google Pay.