Zoo project to include fundraising goals update by Sacramento Zoological Society; Name of the zoo slated for approval

The Sacramento Zoological Society has held many fundraiser including this one at local Wendy's outlets  in October to help raise their $50 million toward the construction of the first phase of the $300 million zoo  in Elk Grove. |

At tomorrow's Elk Grove City Council meeting, an update on the Sacramento Zoo relocation project will be presented. One of the most crucial topics to be covered is the fundraising activity of the Sacramento Zoological Society (SZS), the zoo's operator.

 

As part of the agreement with Elk Grove to pay the $300 million-plus cost for construction of the first phase of the new facility, the SZS must raise $50 million. The report includes an update on their pledges.

As noted in the staff report, the SZS had met its obligation to have $17.5 million in pledges by January 1. 

 

The pledges, which were examined by unnamed city staff and not an independent certified public accounting audit, mean parties have committed to giving the money to the SZS in the future.

 

As part of the agreement, the SZS must remit funds to the city on a quarterly basis. While the SZS claims to have $17.5 million, the cash they remitted to the city is only $1.9 million, meaning they still need to secure $48.1 million for their share. 

 

The largest pledge, which has not been collected, is pledge 26299, made on April 25, 2024, for $10 million. The end date of the annual pledge is December 31, 2034, but nothing has been paid to date.

 

The pledge report shows the SZS received $3.6 million in donations. The difference between the $3.6 million raised and the $1.9 million remitted to Elk Grove is for current zoo operations. 

 

Of the 94 donations greater than $10,000, 31 have paid off their balance. The other contributions are to be paid off as late as 2034.  

 

During several of the meetings leading to the zoo's approval, City Councilmember Kevin Spease sought reassurances from the SZS that the $50 million would be cash in hand for construction and not pledges. See the exchange between Spease and SZS officials in the video below.

 

As part of the Wednesday hearing, the city council will also consider adopting the zoo's official name. A city council subcommittee of Mayor Bobbie Singh-Allen and Councilman Rod Brewer, with the help of a public relations consultant, developed the proposed name for the zoo.

 

Singh-Allen, Brewer, and the consultant developed the name "The Greater Sacramento Zoo at Elk Grove."  


You may not like us, but here you are!
Follow us on Threads @ElkGroveNewsnet
Follow us on BlueSky @Elkgrovenews.bsky.social
Follow us on Spoutible @ElkGroveNews
Follow us on YouTube @ElkGroveNews
Copyright by Elk Grove News © 2025. All rights reserved.

Related

Government & Politics 8831979923549508183

Post a Comment Default Comments

1 comment

Renegade said...

Pledges aren't money. It's simply a legally unenforceable promise. Anyone pledging can renege on that promise at anytime. A pledgee can die, come upon hard times or simply decide their money could be spent better elsewhere. The city should not begin the buildout of this zoo until that entire $50M is cash in hand. Otherwise, citizens will be asked to fund it with MORE of our tax money. Councilman Spease was correct to demand that the city have all of the $50M in hand before shovels hit the dirt. No one else on that dais joined him. Keep in mind taxpayers will be funding the other $250M cost regardless of whether the SZS meets it's quota.

Follow Us

Popular

Archives

Elk Grove News Minute Podcast


Elk Grove News Podcast




item